This guide explains the decisions that matter and how to handle them clearly before they become costly site changes.
Create one documented source of truth
Before construction, approve the brief, drawings, specification, BOQ and programme in a shared digital location. Nominate one decision-maker and one authorised project contact so instructions from family members do not conflict.
Agree how remote reporting will work
For clients living in Dubai, Abu Dhabi or elsewhere, set a regular Sri Lanka–UAE call time and request dated photos, short site videos, progress notes and updated cost records. Important concealed work should be reviewed before it is covered.
Connect payments to verified progress
Use written milestones and confirm completed quantities or agreed deliverables before releasing each payment. Record variations with their cost and time effect, and retain important approvals so the project remains understandable even when you cannot visit frequently.